CAP wrote:Took place between 1st & 14th November, any further details please post.
I'm particularly keen to know if this was a wet or dry-dock event.
Actually it was much longer than that (about 6.5 weeks) and, as far as I know, was never
scheduled for those dates. It was originally scheduled to start
around Nov 10 and last about 17 days. However, the UK shipyard
unions were still peeved about the 1977 refit being shifted to Bayonne
and demanded more work to compensate them for the work they lost in
1977. Cunard caved in to the demands and canclled the scheduled
crossings of Oct 30-Nov 4 (Westbound) and the Novemebr 4-10 (Eastbound)
to extend the refit. (I was booked on the cancelled Oct 30-Nov 4
crossing and was directly affected by the changes). This extended the
planned refit by 11 days. However, the unions dragged their feet on the
job by "working to rule" and the work still had not been completed when
QE2 finally returned to service on December 16 in order to get to New
York in time for the highly profitable annual Christmas-New Year's
cruise that was scheduled to depart New York on December 21.
Workers were still on board during the crossing to New York and QE2
received a lot of negative publicity, especially in the New York Times.
(The Montreal Gazette carried the NY Times reports as well). So, QE2
was out of sevice from October 29, 1978 when she returned to
Southampton from a Canary Islands Cruise (that I was also booked on)
until December 16.
It had to be a
dry docking because that is the refit where the
uderwater hull and boot-topping weres first painted blue using a new
type of paint that Cunard was testing with/for the British Admiralty.